Reports

Trainee Progress Report

November 15, 2021 | 1 min read

The Trainee Progress Report shows how far each learner has progressed through a course, giving you visibility into who is on track and who may need a nudge.

Steps

  1. Go to Reports → Course.
  2. In the Course dropdown, select the relevant course.
  3. In the Report dropdown, select Progress.
  4. Apply any Advanced Filters and Enrollment status as needed.
  5. Select the display type – Tabular or Graphical – and click Submit.

Export and Save

  • Click Export to download the report.
  • To save the report, enter a name in the text box and click Save. Saved reports are accessible under Reports → Saved Reports.

Trainee Progress Report in AlphaLearn LMS